March 2014

March 2014 Birmingham Northern Beltline Community Outreach Group Meeting Notes March 13, 2014 Click the button below to download the meeting notes from this community outreach event. Download Meeting Notes

February thru March 2014

Monthly Construction and Environmental Update West End (Station 2137 at SR 79 to Station 2190) Gas utility contractor began relocation work near SR 79 utilizing both open trench and trenchless methods of installation Utility construction-related traffic control and...

April 2014

Monthly Construction and Environmental Update West End (Station 2137 at SR 79 to Station 2190) Gas utility contractor relocation work ongoing near SR 79 utilizing both open trench and directional bore methods of installation. Utility construction-related traffic...

May 2014

Monthly Construction and Environmental Update West End (Station 2137 at SR 79 to Station 2190) Gas utility contractor relocation work ongoing near SR 79 utilizing both open trench and directional bore methods of installation. Utility construction-related traffic...

June 2014

Monthly Construction and Environmental Update West End (Station 2137 at SR 79 to Station 2190) Gas utility relocation work ongoing near SR 79 utilizing both open trench and directional bore methods of installation. Utility construction-related traffic control and...

July 2014

Monthly Construction and Environmental Update West End (Station 2137 at SR 79 to Station 2190) Gas utility contractor relocation work ongoing near SR 79 utilizing both open trench and directional bore methods of installation. Utility construction-related traffic...