News & Updates

Community Involvement

Learn about the Community Outreach Group (COG). View community updates.

Project News

Construction Updates

February 2017

February 24th, 2017|

Monthly Construction and Environmental Update APD-1602(551) PS 1175 SR-959 From SR79 to SR75 Pinson, AL ALDOT requested termination of General NPDES Permit ALR10AC66 on November 4, 2016. The termination was granted by ADEM effective November

October 2016

October 29th, 2016|

Monthly Construction and Environmental Update West End (SR 79) Construction safety zone in effect along SR79. Speed limit reduced to 45 mph. Culvert slopes west of SR79 remain stabilized with permanent vegetation, Rolled Erosion Control

September 2016

September 25th, 2016|

Monthly Construction and Environmental Update West End (SR 79) Construction safety zone in effect along SR79. Speed limit reduced to 45 mph. Culvert slopes west of SR79 remain stabilized with permanent vegetation, Rolled Erosion

August 2016

August 30th, 2016|

Monthly Construction and Environmental Update West End (SR 79) Construction safety zone in effect along SR79. Speed limit reduced to 45 mph. Traffic remains re-routed over the western section of culvert, but will be

June 2016

June 30th, 2016|

Monthly Construction and Environmental Update West End (SR 79) Construction safety zone in effect along SR79. Speed limit reduced to 45 mph. Traffic remains re-routed over the completed section of new roadway. Section of

May 2016

May 30th, 2016|

Monthly Construction and Environmental Update West End (SR 79) Construction safety zone in effect along SR79. Speed limit reduced to 45 mph. Traffic remains re-routed over the completed section of new roadway. Section of

April 2016

April 30th, 2016|

Monthly Construction and Environmental Update West End (SR 79) Construction safety zone in effect along SR79. Speed limit reduced to 45 mph. State Troopers are patrolling area. Traffic remains re-routed over the completed section

March 2016

March 30th, 2016|

Monthly Construction and Environmental Update West End (SR 79) Construction safety zone in effect along SR79. Speed limit reduced to 45 mph. State Troopers are patrolling area and issuing tickets. Traffic remains re-routed over

February 2016

February 28th, 2016|

Monthly Construction and Environmental Update West End (SR 79) Construction safety zone in effect along SR79. Speed limit reduced to 45 mph. State Troopers are patrolling area and issuing tickets. Traffic remains re-routed over

December 2015

December 30th, 2015|

Monthly Construction and Environmental Update West End (SR 79) Traffic re-routed over the completed section of new roadway on December 11, 2015. Construction safety zone in effect along SR79. Speed limit reduced to 45

November 2015

November 30th, 2015|

Monthly Construction and Environmental Update West End (SR 79) Construction safety zone in effect along SR79. Speed limit reduced to 45 mph. State Troopers are patrolling area and issuing tickets. Section of culvert west

October 2015

October 30th, 2015|

Monthly Construction and Environmental Update West End (SR 79) Section of culvert west of SR79 completed. Fill material completed over culvert for road bed. Slopes are stabilized with permanent seed, rolled erosion control products,

August 2015

August 30th, 2015|

Monthly Construction and Environmental Update West End (SR 79) Culvert construction west of SR79 completed. Fill material being placed over culvert for road bed. Slopes are stabilized with permanent seed, Rolled Erosion Control Netting,

July 2015

July 30th, 2015|

Monthly Construction and Environmental Update West End (SR 79) Utility work related to fiber optic lines and gas relocation work completed. Jefferson County water line installation (under separate NPDES permit) completed near SR 79

June 2015

June 30th, 2015|

Monthly Construction and Environmental Update West End (SR 79) Utility work related to fiber optic lines and gas relocation work ongoing. Jefferson County water line installation (under separate NPDES permit) completed near SR 79

May 2015

May 30th, 2015|

Monthly Construction and Environmental Update West End (SR 79) Utility work related to fiber optic lines and gas relocation work ongoing. Jefferson County water line installation (under separate NPDES permit) ongoing near SR 79

April 2015

April 30th, 2015|

Monthly Construction and Environmental Update West End (SR 79) Utility work related to fiber optic lines and gas relocation work ongoing. Jefferson County water line installation (under separate NPDES permit) ongoing near SR 79

March 2015

March 30th, 2015|

Monthly Construction and Environmental Update West End (SR 79) Utility work related to fiber optic lines and gas relocation work ongoing. Jefferson County water line installation (under separate NPDES permit) ongoing near SR 79

December 2014

December 30th, 2014|

Monthly Construction and Environmental Update West End (SR 79) Utility work related to fiber optic lines has delayed other utility relocation work. Jefferson County water line installation (under separate NPDES permit) ongoing near SR

November 2014

November 30th, 2014|

Monthly Construction and Environmental Update West End (SR 79) Utility work regarding repositioning of AT&T fiber optic lines remains un-resolved. Gas utility relocation work ceased due to AT&T fiber optic delay. Jefferson County water

October 2014

October 30th, 2014|

Monthly Construction and Environmental Update West End (SR 79) Utility delay regarding repositioning of AT&T fiber optic lines. Utilities working on resolution but effect on project progress not known at this time. Gas utility

August and September 2014

September 30th, 2014|

Monthly Construction and Environmental Update West End (SR 79)West End (SR 79) Cross drain pipe and culvert extensions on south end of SR 79 have been completed. Temporary Sediment Basins 31 and 32 (west

July 2014

July 30th, 2014|

Monthly Construction and Environmental Update West End (Station 2137 at SR 79 to Station 2190) Gas utility contractor relocation work ongoing near SR 79 utilizing both open trench and directional bore methods of installation.

June 2014

June 30th, 2014|

Monthly Construction and Environmental Update West End (Station 2137 at SR 79 to Station 2190) Gas utility relocation work ongoing near SR 79 utilizing both open trench and directional bore methods of installation. Utility

May 2014

May 30th, 2014|

Monthly Construction and Environmental Update West End (Station 2137 at SR 79 to Station 2190) Gas utility contractor relocation work ongoing near SR 79 utilizing both open trench and directional bore methods of installation.

April 2014

April 30th, 2014|

Monthly Construction and Environmental Update West End (Station 2137 at SR 79 to Station 2190) Gas utility contractor relocation work ongoing near SR 79 utilizing both open trench and directional bore methods of installation.

February thru March 2014

March 30th, 2014|

Monthly Construction and Environmental Update West End (Station 2137 at SR 79 to Station 2190) Gas utility contractor began relocation work near SR 79 utilizing both open trench and trenchless methods of installation Utility