Monthly Construction and Environmental Update

APD-1602(551) PS 1175
SR-959
From SR79 to SR75
Pinson, AL

  • ALDOT requested termination of General NPDES Permit ALR10AC66 on November 4, 2016. The termination was granted by ADEM effective November 15, 2016. (See Attached).
  • ALDOT planted 1000 loblolly pine seedlings on one of the backslopes on the east end of the project in December 2016.
  • Final layer of asphalt completed.
  • The final inspection was completed and the project turned over to Maintenance on February 16, 2017.